Taconic High School Educational Programs Needs Study, May 2012

The New England School Development Council (NESDEC) was contracted by the City of Pittsfield’s School District to complete a comprehensive needs assessment of the Chapter 74 Programs that are offered or to be offered in a new Taconic High School. Download the NESDEC Final Report here.

The high school feasibility study

During the Spring of 2011, members of the SBNC held several community outreach meetings. As part of those meetings, a condensed brochure of important information and a PowerPoint presentation were delivered.  Both are provided via the links below.

High School Educational Visioning and Master Planning

In 2007, the City entered into a contract with Dore and Whittier Architects, Inc, to provide an analysis and recommendations regarding public high school education in Pittsfield, with a particular emphasis on the potential and/or opportunities for school consolidation. Over five working days, 39 individuals—representing school and community perspectives—were led by educational planner, Frank Locker, through a series of exercises. The main goal was to evaluate and determine the long range disposition of secondary education in Pittsfield.

The results of the study, presented in a public forum in May of 2008, is included in this report. For comparative purposes only, a series of conceptual design options was prepared by Dore and Whittier with estimated costs associated with each option. The core of this work, however, has set the stage for future planning related to educational plans and programs.

MSBA Process

School construction is guided by a process outlined by the MSBA.   This consists of five basic phases:

  • Phase 1:   Identify the problem
  • Phase 2    Verify the problem
  • Phase 3:   Collaborate on solution
  • Phase 4:   Agree upon a solution
  • Phase 5:   Implement agreed-upon solution

Over the last several years, Pittsfield has worked through Phases 1 & 2 and is currently in Phase 3, that being developing a solution. This phase has begun with initial site investigations, a Labor Market Study, the development of a draft Educational Program, and initial community outreach. Attached below is a schematic provided by Skanska USA, our Owner’s Project Manager. (Click to enlarge.)